Power Supply User Manual

55
7. Now actuate the mains input miniature circuit breakers
(no. 2, p. 26/27) on each UPS one after the other.
Move them to the "ON" position.
8. Move the “maintenance switch” manual bypass
switches (no. 3, p. 26/27) on the back of each
UPS to the “UPS” position. Finally, fasten the
covers on each UPS again using the 4 respective
screws that were previously removed.
i
The voltage supply of the parallel operation
busbar now takes place via the integrated
electronic bypass switches of the UPS systems
used. Check this operating state on the display
panel of each UPS = Bypass (chapter 6.1.3).
9. Now actuate your central external manual bypass:
Switch from the “Bypass position to “UPS operation”,
i.e. connect your load busbar to the UPS parallel
operation busbar.
i
This is done using a manual bypass switch with
overlapping switching contacts without any
interruption in the load voltage, i.e. completely
interruption-free.
10. Now switch on the inverters of the UPS systems.
To do this, press the ON pushbutton of each UPS
for approx. 2 seconds one after the other.
i
After switching on, each UPS carries out a self-
test and synchronizes itself with the parallel
operation busbar, while the LED’s for load and
battery state switch on and off consecutively in
increasing order. After the successful
synchronization of all inverters, the Inverter LED
on each UPS lights up a few seconds later,
whereby the UPS systems now work in parallel
normal operating mode and supply the parallel
operation / load busbar with UPS voltage.
The central external manual bypass switch must
be protected against accidental actuation. Never
actuate it when the UPS systems are in inverter
mode.