INSTALLATION
19
B.6. Double Unit Installation AP40BC250-2-12, BCCP-2
BCCP-2
Installation procedures are similar with the ones for the single unit. Each of the two evaporators is fed by one
condensing unit. A double unit has two evaporator frames (one per compartment) and two blower frames (one per
compartment) controlled by a single control panel.
The difference is made by the double number of power cables and air probe cables. The two frames to be
installed by the control board are marked # 1. The other two frames to be installed on the back are marked # 2 (see
PHOTO B.5.1 and PHOTO B.5.2). If the markings are lost or missing and you need to select the frames to be installed
close to the controller, look for the ones with extra long cables. If the frames are installed improperly, the feeding cables
will be short. Drill holes through the partition walls above the top of the frames. Run the cables with connectors through,
and plug them according to the color codes. Protect the cables from the rough edges of the drilled holes into the partition
walls.