Figure 15: Bottom of gateway receiver
8. Remove the M12 cap from the M12 receptacle on the bottom of the network gateway receiver and discard the cap.
9. Connect the M12 plug connector assembly to the M12 receptacle and tighten the locking ring in a clockwise
direction until nger tight.
10. Connect the 308 connector on the other end of the power cable to the 308 connector of the AC-to-DC power supply
and snap the anti-tamper collar over the connection.
11. Connect the power cord to the power supply and then plug the three prong male end of the power cord into a
120V AC power source. The LED indicator above the M12 connection turns on with a steady green light, indicating
the gateway power is on (Figure 16).
OTE:N A red blinking light indicates the gateway is on internal backup battery power. No light indicates the
gateway is not receiving power.
Figure 16: Powered gateway
The M12 connection is complete.