Technical data

Commissioning
30 POTTERTON COMMERCIAL
120-393 632.4 04.08 Fh
6. Commissioning
Danger! The commissioning must only be carried out by a heating
specialist! The heating specialist checks tightness of the installati-
on, correct function of all regulating, control and safety devices.
See commissioning sheet at rear of manual!
6.1 Switching on
Danger of scalding! Hot water may exit from the blow pipe of the
safety valve.
1. Switch on boiler isolator switch
2. Open gas shut-off valve
3. Open front panel cover and switch on operating switch on the
front panel of the boiler
4. Select the operation mode automatic operation with the ope-
ration mode button on the control unit
.
5. Set the required room temperature on the rotating knob of the
control unit
6.2 Temperatures for heating and DHW
The information in the section programming for setting the tem-
peratures for heating and DHW.
For DHW processing a setting onto 55°C is recommended.
You can adjust hours/minutes for DHW in time program 4. For re-
asons of comfort, the time program for DHW should start one
hour before time programe 1 and 2 start.
6.3 Individual time program
The boiler can be commissioned having its standard values.
For adjusting parametres like individual time program, please con-
sider the information given in the section Programming.
Auto