Technical data

Commissioning
120-393 632.4 04.08 Fh
PARAMOUNT two 30 - 115 kW 31
6.4 Programming of necessary parameters
Normally, the control parameters do not have to be modified (Ap-
plication example). Only date/time and possibly the time program-
mes have to be modified.
Setting of the parameters is described in the section programming.
6.5 Emergency operation (Manual operation)
Setting the emergency operation of the plant>
• Press OK-button
• Select menu point maintenance/service
• Set function manual operation (7140) to ""ON"
Heating circuit pumps have been switched on and mixer is set to
manual opration
Using the operation mode "manual operation" you can choose a no-
minal temperature value for it:
Press button "info"
Acknowledge selection with OK
Adjust nominal value by using rotating knob
Acknowledge setting with OK.
See also section Explanations for setting table.
6.6 Instruction for the customer
Instruction
The customer should be instructed in the operation of the boiler
and the function of the safety devices. The following should be
pointed out:
The air inlet must not be restricted;
Flammable materials and liquids must not be stored in the vici-
nity of the boiler
The customer has to carry out the following control checks him-
self>:
– Pressure check on the pressure gauge;
– Check the discharge from the safety valve
Only approved gas installers may carry out the inspection and
maintenance.
Documents
The documents, belonging to the boiler, have to be handed over
with the instructions they have to be kept in the installation
room of the boiler.
Copy the commissioning sheet with confirmation and legally
binding signature to the customer. All components have been in-
stalled according to the instruction of the manufacturer. The
whole plant complies with the relevant British Standards and
current building regulations.