Operation Manual
Table Of Contents
- Title Page
- Table of Contents
- Safety
- Unpacking
- Product Description
- Electrical Connections
- Install the MIC (standard) PSU
- MIC PSU Overview
- About the MIC Shielded Composite Cable
- Composite Cable Color-coding
- Earth Link on PCB
- Fuse Ratings
- Alarm Inputs
- Layout of MIC Power Supply Units (PSUs)
- Installation Warnings and Prerequisites
- Installation Instructions (Power Supply)
- Commissioning the Camera with Heater Option Fitted
- Simultaneous IP and Analog Video/Control ("Hybrid" Operation)
- Fit the Sunshield (MIC612)
- Getting Started
- Controlling the Camera
- On-Screen Display (OSD) Menus (Bosch Protocol)
- On-Screen Display (OSD) Menus (Pelco Protocol)
- Operation of the Thermal Camera
- Common User Commands
- Advanced Features
- Maintenance and Troubleshooting
- Technical data
- Appendices
- Back Page
5. Secure the enclosure to the mounting surface using four (4) M6 stainless steel screws and
washers (not supplied), which fit through the large holes in the enclosure.
Notice!
If you are securing the power supply enclosure in a vertical position (for example, on a wall),
one person should hold the enclosure lid while another secures the enclosure body in place,
to avoid damage to any part of the enclosure, and/or injury to the installer(s).
6. Unscrew the two (2) M3 screws on the internal high voltage input head-end shield (marked
with "Danger") covering the mains cable terminal HD1; retain the screws.
Figure 5.6: Enclosure showing shield and earth core cable between earth terminal post and enclosure lid
Number
Description
1 Earth core cable to enclosure lid
2 Internal shield
3 Earth termination post
7. Remove the internal shield and set it nearby, outside of the PSU enclosure. You can now
access the hole for the power cable and the M20 blanking plug covering the hole.
8. Remove the blanking plug covering the hole for the power cable. Install suitable (metal)
conduit (not supplied) in the hole. Secure the conduit as recommended by the conduit
manufacturer.
!
Caution!
Only installations with conduit meet UL standards. If you choose to use a power cord without
conduit (not recommended), fit the 1/2 in. NPT cable gland (supplied) in place of the
blanking plug. Note: It is easier to fit the power cord through the cable gland outside of the
enclosure, and then attach the gland to the enclosure. Ensure that the cable glands have
sufficient room to allow for the cables to enter (approximately 60 mm on either side of the
enclosure).
9. Prepare the power cable as needed, and then feed the cable into the enclosure.
10. Connect the Live and Neutral cores to the correct screw terminals on terminal block HD1
as identified in the table below and printed on the PCB. Observe polarity and voltage.
MIC612 Thermal Camera Install the MIC (standard) PSU | en 21
Bosch Security Systems Operation Manual 2016.03 | 2.2 | F.01U.249.416