HIGH LEVEL SIDE & REAR INSTALLATION
A
ssemble the flue generally as follows:
1. Position boiler check that all water connections and proposed flue position are according to clearances
specified.
2. Mark the flue position on the wall.
3. Move the boiler away from the wall and using a diamond tipped core drill drill a 6" 150mm hole in the wall
ensuring the hole is level.
4. Remove the top panels of the boiler and fit the appropriate blanking plate to rear panel using the nuts and
washers provided.
5. Fit the boiler offtake gasket to the four studs and fit offtake spigot with the four nuts and washers provided.
6. Ensure the flue exhaust seal is in position and undamaged.
Lubricate with a mild detergent.
7. Fit the vertical flue offtake plate to the rear top panel of the boiler and fit the assembly into position over the
vertical offtake spigot.
8. Take the 1000mm vertical extension and fit an O Ring seal to the outer duct, lubricate with a mild detergent
and ensure that the flue exhaust seal is fitted to the inner duct undamaged and in the correct orientation.
9. With the seals fitted slide the extension into the offtake socket external O Ring end first.