12. Take the extension, fit O Ring seals to the outer duct and ensure that the flue exhaust seal is fitted to
inner ducts undamaged and in the correct orientation. Lubricate all seals with a mild detergent.
13. With both seals fitted slide the 1st extension into position.
14. Add extensions until the joint nearest the ceiling is 150mm away. Slide the ceiling trim onto this last
extension ensuring it is the correct way up (screws at the top).
15. Using a 3mm drill bit drill 2 holes per extension top and bottom and secure with self tapping screws
supplied.
16. From within the roof space if space permits: Fit next extension(s) in line with points 12 to 13
17. From outside lower Flue Terminal into roof opening having previously removed the rain cap, air entry Rain
shield and Cravat.
IMPORTANT ENSURE ALL SEALS ARE IN POSITION
18. From within the roof space align the terminal with the extension beneath and push fully home.
19. Secure the terminal to the roof timbers with the optional Flue Support Quadrant Plate Assembly. Adjust
the angle to suit the pitch of the roof.
20. Drill the outer air ducts to secure extension to extension by 4 self tapping screws.
21. Using the clips supplied fix the air duct to the burner spigot and vertical flue offtake spigot.
Continue with the rest of the installation.
BOULTER BOILERS CAMRAY 5
PAGE 37