User guide

Fig. 8.3a Baffle Arrangement
To ensure correct placement of baffles ensure that castellated edges are positioned towards the heat
exchanger and:
1. All baffles are horizontal
2. All baffle handles are in the forward position.
BOULTER BUDERUS CAMRAY 5
PAGE 45
10:1 FAULT FINDING
If the Boiler fails to start, make the following checks before calling a service engineer:-
1. Is there sufficient fuel in the storage tank?
2. Are all fuel supply valves open (turned fully anti-clockwise) and ball valves open?
3. Is the mains electricity supply switched on?