Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 2012/10
We reserve the right to make any changes due to technical modifications.
Boiler block assembly7
Installing thermal insulation
z Position the thermal insulation over the boiler block.
z Push the thermal insulation below the boiler block in
the direction of the arrow.
z Position the thermal insulation tabs in front of the top
tie-bar and draw them together with a spring clip.
Fitting the side panels
The side panels are fitted identically on each side (r.h.
side panel shown here)
z Push the snap nut onto the angled sheet steel of the
side panel until it locks into the hole provided.
z Push the side panel into the angled part of the bottom
cross bar.
Fig. 37 Installing thermal insulation
1 Spring clip
2 Thermal insulation tabs
2
1
Fig. 38 Positioning snap nut (here: r.h. side panel)
Fig. 39 Push in the bottom front corner of the side panel
1 Angled part of the bottom cross bar