Boiler installation 8
35
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano G215 US oil/gas-fired boilers • Issue 2012/10
8.2 Installation of water connections
8.2.1 Installing B-Kit:
The relief valve and the pressure/temperature gauge are
mounted on the conversion nipple (included in B-Kit) on
the VK boiler supply connection as follows:
z Measure length of thread on R1¼" × 1¼" NPT
double nipple.
z Seal supply manifold to connection VK with the long
side to the boiler.
z Seal conversion nipple on boiler inlet VK.
z Seal pressure/temperature gauge to conversion
nipple.
8.2.2 Installation of boiler drain (included in B-Kit)
z Install the boiler fill and drain valve with seal to
connector EL.
z Seal boiler drain to connection EL.
Fig. 46 Installing B-Kit
1 Supply manifold
2 Pressure/temperature gauge
1
2
VK
RK
Fig. 47 Installing B-Kit
1 90°-elbow 1¼" NPT
2 Pressure relief valve
3 Conversion nipple 1" x ¾"
1
2
3
NOTICE
Do not install the pressure relief valve until
after the leak test (Î Chapter 8.3,
page 36).
The pressure relief valve must be installed
in a vertical position.
Fig. 48 Installation of boiler drain
EL