VIII Gas Piping
Gaspipingtotheboilermustbesizedtodeliveradequategasfortheboilertoreatthenameplateinputataninlet
pressurebetweentheminimumandmaximumvaluesshownontheratingplate.Formoreinformationongasline
sizing,consulttheutilityortheNationalFuelGasCode.
Figure8.1showstypicalgaspipingconnectiontotheFCMboiler.Asedimenttrapmustbeinstalledupstreamofallgas
controls.Installthefactoryprovidedmanualshut-offvalveoutsidethejacketwithagroundjointunionasshown.
Theboileranditsgasconnectionmustbeleaktestedbeforeplacingtheboilerinoperation.Whendoingthis,theboiler
anditsindividualshut-offmustbedisconnectedfromtherestofthesystemduringanypressuretestingofthatsystem
atpressuresinexcessof½psi.Whenpressuretestingthegassystematpressuresof½psiorless,isolatetheboiler
fromthegassupplysystembyclosingitsindividualmanualshut-offvalve.
Figure 8.1: Gas Connection To Boiler