START-UP CHECKLIST FOR 30XA LIQUID CHILLERS
A. PROJECT INFORMATION
Job Name ______________________________________
Address ________________________________________
City __________________ State ________ Zip ________
Installing Contractor_______________________________
Sales Office _____________________________________
Start-up Performed By _____________________________
Design Information
Unit
Model _______________________________________ Serial ______________________________________
Compressors
Compressor A
Model _______________________________________ Serial ______________________________________
Compressor B
Model _______________________________________ Serial ______________________________________
Compressor C
Model _______________________________________ Serial ______________________________________
Cooler
Model _______________________________________ Serial ______________________________________
B. PRELIMINARY EQUIPMENT CHECK (This section to be completed by installing contractor)
1. Is there any physical damage? Ye s No
Will this prevent start-up? Ye s No
Description
__________________________________________________________________________________________
2. Unit is installed level as per the installation instructions. Ye s No
3. Power supply agrees with the unit nameplate. Ye s No
4. Correct control voltage ________vac. Ye s No
5. Electrical power wiring is installed properly. Ye s No
6. Unit is properly grounded. Ye s No
7. Electrical circuit protection has been sized and installed properly. Yes No
8. All terminals are tight. Ye s No
9. All plug assemblies are tight. Ye s No
10. All cables, thermistors and transducers have been inspected for cross wires. Ye s No
11. All thermistors are fully inserted into wells. Ye s No
12. Oil separator heaters energized for 24 hours before start-up. Ye s No
13. Relief valve vent piping per local codes. Ye s No
Chilled Water System Check
1. All chilled water valves are open. Ye s No
2. All piping is connected properly. Yes No
3. All air has been purged from the system. Ye s No
4. Chilled water pump is operating with the correct rotation. Ye s No
5. Chilled water pump starter controlled by chiller. Ye s No
6. Chilled water flow switch operational. Ye s No
7. Inlet piping to cooler includes a 20 mesh strainer. Ye s No
8. Water loop volume greater than 3 gal/ton (40 L/kW) for air conditioning
or 6 gal/ton (80 L/kW) for process cooling and low ambient operation. Yes No
9. Proper loop freeze protection provided to ____ F (C).
Antifreeze type__________________ Concentration _____%. Yes No
(If antifreeze solution is not utilized on 30XA machines and the
minimum outdoor ambient is below 32 F (0 C) then items 10 and 11
have to be completed to provide cooler freeze protection to –20 F (–28.9 C).
Refer to Installation Instructions for proper cooler winterization procedure.)
10. Outdoor piping wrapped with electric heater tape. Ye s No
11. Cooler heaters installed and operational. Ye s No
12. Is the Unit equipped with low ambient head pressure control? Ye s No
a. If yes, are wind baffles installed? Ye s No
CAPACITY EWT LWT FLUID TYPE FLOW RATE P.D. AMBIENT
Cooler