START-UP CHECKLIST FOR 30MP LIQUID CHILLER
(Remove and use for job file.)
A. Preliminary Information
JOB NAME _____________________________
LOCATION _____________________________
INSTALLING CONTRACTOR _______________
DISTRIBUTOR __________________________
START-UP PERFORMED BY _______________
B. Preliminary Equipment Check (Yes or No)
Is there any shipping damage?
If so, where
_______________________________________
Was it noted on the freight bill?
YES NO
Has a claim been filed with the shipper?
YES NO
Will this damage prevent unit start-up?
YES NO
Check power supply. Does it agree with unit?
YES NO
Has the circuit protection been sized and installed properly?
YES NO
Are the power wires to the unit sized and installed properly?
YES NO
Has the ground wire been connected?
YES NO
Are all electrical terminals tight?
YES NO
System fluid volume in the loop ____________________gal (l)
Does this meet installation guide requirements?
YES NO
Water system cleaned per installation guide?
YES NO
Minimum flow rates verified per installation guide?
YES NO
In-line minimum 40-mesh strainer installed within 10 ft of the cooler/condenser water inlet?
Cooler:
YES NO
Condenser:
YES NO
Air separation / bleed devices installed per installation guide?
YES NO
C. Cooler Loop Freeze Protection (if required)
Gallons (liters) added:________________
Piping includes electric tape heaters if piping is exposed to temperatures below freezing?
YES NO
On brine units, has the cooler fluid been properly protected from freezing to at least 15 F (8.3 C) below the lowest
anticipated leaving fluid temperature set point?
YES NO
Have the main base board, energy management module (option) and control relay connections been checked for
tightness?