Advanced Drain
Install composite drainage mats in accordance with manufacturer’s instructions at locations
indicated on the Drawings.
Install composite drainage mats:
-To allow flow of water in all directions within drainage core.
- To prevent soil from entering drainage core while providing ample flow of water.
Secure composite drainage mats to surfaces with construction adhesive or termination bars in
accordance with manufacturer’s instructions.
Butt composite drainage mats together without overlapping.
Apply construction adhesive on fabric overlap for sealing adjacent composite drainage mats to
prevent soil intrusion at joints.
Protect installed composite drainage mats from damage during construction.
RAM Vent
Unroll RAM Vent™ along the perimeter of the footings on top of the soil.
Lay a cross piece of RAM Vent™ through the center parallel to the longest wall every 15 to 20
feet. Then, overlay the subfloor with a vapor barrier extending up the wall.
Cut a 3” (8cm) hole in the vapor barrier near the most appropriate corner. Next, glue a 4”
(10cm) flanged riser pipe with a detachable cap to the vapor barrier and sitting on top of RAM
Vent™ (The pipe stub should be long enough to extend above the top of where the slab is
poured). Then, pour the slab. Finally, extend the vent pipe through the roof.
Additional Instruction Make sure to seal any cracks/ seams etc. on top of the concrete with a
sealant, such as silicone.
Mortar Break DT
Install mortar deflection devices as part of masonry wall construction and in accordance with
manufacturer’s installation instructions.
Install in cavities at [all through wall masonry flashings with weep holes.] [locations detailed on
Drawings.]
Place deflection strips horizontally and diagonally directly on flashings.
Weep Vents
Install weep vents as part of masonry wall construction and in accordance with manufacturer’s
installation instructions. Coordinate with installation of through wall flashings.
Locate weep vents at [wall bases, above door and window openings, above bond beams, and
other through wall flashings.] [At locations detailed on Drawings.] Space at [_____] [inches]
[mm] maximum.
Embed weep vents in vertical mortar head joints. Tool joints to prevent obstruction of weep
spouts.