VERTICAL SIDING INSTALLATION
At the peak of the gable, drop a chalk line perpendicular to the starter
strip. To determine where to start the first panel – measure from chalk
line along the starter strip in units of 5" (127 mm) until you get to a
point where the measurement to the J-channel is less than 5" (127 mm).
Mark that point with a pencil. Measure back toward the center of the
gable from that point 1-1/4" (32 mm), and draw a vertical line, parallel
to the line dropped from the gable peak. This line is the position of the
edge of the nail hem on the first panel.
NOTES
Measure the first panel, cut and
install. Install subsequent panels,
increasing in length as the peak
rises. Every 3 panels be sure to
check for plumb and also measure
to the center chalk line to ensure
that you are going to arrive at
the peak with a center groove in
line with it. Make needed small
adjustments by pushing the panels
“in” or “out” within the lock. The
lock should face away from the
general viewing area.
Vertical line marked.
First panel
measured and
installed.
Measured back
1-1/4" (32 mm).
General viewing area.
Slight lock adjustments in or out.
Marks for
5" (127 mm)
increments.