Technical data

Chapter 5 Operation
31
Chapter 5 Operation
Warning:
To ensure operational safety, conduct the initial
on-grid testing before operating on the CPS
SC100KT-O/US-480.
5.1 Start-up and shut-down
5.1.1 Start-up
Turn on the DC and AC circuit breakers.
Manual start-up: Manual start-up is required after initial
installation or manual (fault) shut-down.
Move the cursor from the main operation interface to“4
Setting” according to “6.3.6 System setup”. Press ENTER
and go to submenu “1 ON/OFF”. Then move the cursor to
“ON” and press ENTER to start the inverter. Then the
inverter will start up and operate normally if the start-up
condition is met. Otherwise, the inverter stands by.
Automatic start-up: Confirm that the inverter is “ON
State” at first. The inverter will start up automatically when
the output voltage (Default value is 330V, which can be set
up according to “6.3.6 System setup”.) of PV panel meet the
set point, AC power grid is normal, and the ambient
temperature is within allowable operating range.
5.1.2 Shutdown
Manual shut-down : Normally, manual shutdown is not