- Secure temperature controller on boiler-tube of aggregate with 2 screws.
- Pull protecting socket onto the end of outer securing screw of temperature
controller, because the sharp end of screw can cause an accident.
(Fig. 103, 104)
Installation :
- Reassemble aggregate and heating element in opposite order of
disassembly.
- Reinsert electrical connections of temperature controller according to the
status prior to disassembly.
- Screw wire clamp back on.
- Reinsert electrical cover or thermostat cover, secure with screw.
- Push drain water evaporator onto fluid heat-exchange pipe.
Make sure the drain water outlet pipe’s outlet portion reaches in the drain
water evaporator. (Fig. 105)
- Lay refrigerator on its back.
- Drill 2, 3.2mm diameter bores on the freezer mount (where the cooling
aggregate is attached to the freezer compartment) according to the
positioning of bores on the freezer compartment. (Fig. 106)
During this procedure, you must wear protective goggles !