6-3 AUTOCALIBRATION SEQUENCE PRO-
GRAMMING
Up to 40 steps can be programmed with any
combination of four Analyzers.
Figure 6-3. Autocalibration Sequence Programming Setup
From the System Calibration menu use the
keys to move to Calibration sequence
programming… menu line, press (Enter).
Use the keys to move to the Step #:,
enter a step number, press (Enter). Move
to the Calibration procedure type: line and
select from the available list:
NoOp
Zero-Cal
Span-Cal
Zero/Span-Cal
Span1-Cal
Span2-Cal
Span3-Cal
Span4-Cal
END-OF-PGRM
Using the keys, go to the Choose
Analyzer module… menu line, press
(Enter). A list of attached Analyzers to
choose for the current step number will be
displayed. Or, go to the Select all Analyzer
modules! function line. The chosen
analyzer or “All” displays below the line.
Select any one of the Program steps x-xx…
lines to display the currently programmed
steps in groups of 10.
CLD 7.50 ppm
Measure
Back… Result…
-- System Calibration --
Calibration and test procedures…
Calibration sequence programming…
Times for interval operation…
Analyzer module setup…
CLD 7.50 ppm
-- Calibration Se
q
uence Pro
g
rammin
g
--
Step #: 1
Calibration procedure type: Zero-Cal
Choose analyzer module…
Select all analyzer modules!
Program steps 1-10…
Program steps 11-20…
Program steps 21-30…
Program steps 31-40…
Analyzer module: All
Measure
Back…
CLD 7.50 ppm
-- Pro
g
ram ste
p
s 1-10 --
Step#1: Zero-Cal: All
Step#2: Span1-Cal: All
Step#3: Span2-Cal: All
Step#4: Span3-Cal: All
Step#5: Span4-Cal: All
Step#6: NoOp: All
Step#7: END-OF-PGRM
Step#8: END-OF-PGRM
Step#9: END-OF-PGRM
Step#10: END-OF-PGRM
Measure
Back…
Main Menu
System configuration and diagnostics…
System calibration…