Installation Guide

5
Section 2 Installation
Remove existing load wires coming from the home.
Add two double wire lugs to the meter pan which are represented by Lugs 3 and Lug 4 in Figure 2.2
Connect the two existing load wires coming from the home to Lug 3 and Lug 4
Connect L1 wire to Lug 4
Connect L2 wire to Lug 3
Connect U1 to Lug 1
Connect U2 wire to Lug 2
Connect G1 to Ground Lug
Figure 2.2
NOTICE!
The installation must fully comply with all applicable
codes, standards, and regulations.
DANGER!
Verify both UTILITY and ALTERNATE power supplies
are OFF before trying to connect power source and
load lines to the transfer switch. Supply voltages are
extremely high and dangerous. Move handle on EZ-
Connect into OFF position.