5. Commissioning
5−5
Festo P.BE−GDCP−SFC−LACI−PB−EN en 0812NH
5.1.1 Checking the drive
Note
During operation, the drive must not strike a stop without
shock absorption.
· Use shock absorbers or buffers on all stops
(exception: homing to a fixed stop).
· Before commissioning, make sure that drive and con
troller are completely set up and wired and that the
working space is adequate for operation with an effective
load
· Observe the notes in the operating instructions for the
axis used.
5.1.2 Checking the power supply
Caution
Interruption of running tasks due to inadequate load
voltage supply (LOAD POWER DOWN")
· Make sure that the load voltage supply tolerance can be
maintained at full load directly on the voltage terminal of
the SFC−LACI (see section 3.2).
Caution
Loss of reference position due to inadequate logic supply
voltage
· Always carry out a reference run every time the logic
voltage supply is switched on, in order to anchor the
measuring reference system to the reference point
(REF).
The SFC−LACI does not carry out any positioning tasks if it
is not referenced.