LifeRoom Optima Installation Guide
STEP 3A: Marking the Edge
Beam & the Hanging Channel
Set the 3" Edge Beam and Hanging
Channel together as shown on a flat
non-abrasive surface, making sure
the right ends are even; then, tape
the ends together.
STEP 3B: Hook the measuring tape on the end and mark the Edge Beam and Hanging
Channel at 12 3/8“, 24 3/8”, 36 3/8” and so on, marking every 12with a pencil. Mark
the Edge Beam on the backyard-facing front side. These marks will be the CENTER
marks of the mated Roof Panels. The Roof Panels need to be squeezed slightly to line-
up the mated Roof Panel joints to the marks. This is a CRITICAL step when installing
the Roof Panels.