LifeRoom Optima Installation Guide
STEP 6C: Running the Roof
Panels & Pre-formed Flashing
(continued) The pre-punched holes
in the Roof Panel should be lined-up
with the screw groove in the bottom
leg of the Hanging Channel (#B). It is
CRITICAL to align the CENTER of
the MATED ROOF PANEL SEAM
with the 12" marks made on the
Hanging Channel (#B) from STEP 1.
Use one #10x3/8" sms to fasten the
first section of Roof Panel to the
Hanging Channel.
STEP 6D: It is CRITICAL to align the
CENTER of the MATED ROOF PANEL
SEAM with the 12" marks made on the
3” Edge Beam (#F) from STEP 1. Then,
fasten the Roof Panel to the 3" Edge
Beam (#F) using one #10x3/4 tek screw
through BOTH sections of each Roof
Panel.
STEP 6E: Now that you have 3
Roof Panels started on the right side,
take one Pre-formed Flashing, holding
it upright so the 5/16” leg is aligned
into the Flashing Groove in the
Hanging Rail. Slowly lower the
Flashing down to the Roof Panel.
Bend the tabs downward to go into
the Roof Panel grooves to block
leaves.
NOTE: If the tabs do not line-up into the Roof
Panel, check your 12” spacing marks.