- WattMaster Water Source Heat Pump Operations Manual

WattMaster WHP Section 3
Programming 3-21
Holidays
Holiday Day Selection
There are 14 Holiday periods available, organized as a Start Day / Stop Day event. If the
Holiday only lasts one day, enter the same date for the Start & Stop days. There is no
limit to the duration or number of days that can be included in one holiday, other than it
cannot extend past December 31st. If you have a holiday that crosses the end of year
border, you will need to use two holiday periods to accomplish this event.
Holiday Start / Stop Times
Note: Normally there is no schedule in the Loop Controller device. It simply looks at
all the Water Source Heat Pumps for a request to run signal. Scheduling is
maintained separately in each Water Source Heat Pump. If you want to be able
to schedule all Water Source Heat Pumps on and off at the same time, you can
input a schedule on the Loop Controller and it will broadcast that schedule to all
WHPs.
The screens will step through the 14 possible holidays, one
at a time. Line 2 shows which holiday is currently being
programmed.
Line 3 shows which event, the Start Day or Stop Day, is
currently being programmed.
Remember to combine the month and day into a single four
digit value.
EXAMPLE: 0704 = July 4th
1225 = December 25th
The 14 holidays all use the same Holiday Start / Stop
time. The start/stop times are programmed back on the
Week Schedule screens. The holiday schedule screen
appears after the Saturday schedule screen, as you are
stepping through the days of the week.