Hitachi Dynamic Link Manager Software Users Guide for AIX (6.6) (T5208-96010, April 2011)

4. HDLM Operation
212
If the NPIV option is set to on:
Use the
fscsi number to execute the command below. The following
example shows how to place the path in Offline (C) status when the path goes
through
fscsi number 1 (fscsi1):
# /usr/DynamicLinkManager/bin/dlnkmgr offline -hba 00.01
3. Replace the cable.
Note
If you change the port on the Fibre Channel switch or on the storage system,
the path configuration will be changed. Delete the hdisk that are associated
with the cable to be replaced and then reconfigure the device.
4. Place in Online status the path that goes through the replaced cable.
Place in Online status the path that goes through the HBA to which the replaced
cable is connected.
Depending on the NPIV option setting for the
dlmodmset utility checked in step
1, execute one of the following commands:
If the NPIV option is set to
off:
Specify the HBA adapter number and bus number, and then execute the
command shown below. The following example shows how to place the path
in Offline (C) status when the path goes through an HBA whose HBA
adapter number is
08 and whose bus number is 11:
# /usr/DynamicLinkManager/bin/dlnkmgr online -hba 08.11
If the NPIV option is set to
on:
Use the
fscsi number to execute the command below. The following
example shows how to place the path in Offline (C) status when the path goes
through
fscsi number 1 (fscsi1):
# /usr/DynamicLinkManager/bin/dlnkmgr online -hba 00.01
5. Execute the following command to check the path information: