Scheduling Repository Backup
To schedule a repository backup on a network path:
1. From the menu bar, click Administrative Tools to open the drop-down menu.
2. Select Schedule Save Repository and click Add.
Figure 58 Scheduling Repository Backup
3. Follow the wizard to complete the scheduling tasks and click Next.
Figure 59 Schedule Task
4. Set the values for the following applicable options and click Next:
Task name
Select the option Save to a network path using the following credential. By default this
option is selected.
Hyper-V server hostname or IP address
User name
Password
Network path