HP 3PAR Recovery Manager 2.0 Software for Microsoft Hyper-V User Guide (QL226-97701, May 2014)

NOTE: The format of the location of the network path is: \\RemoteHost\<local
drive>\BackupRepository
Figure 60 Schedule Task
5. Set the values for the Schedule, Start time, Recur every , and click Next.
6. Review the summary of task and click Save.
Figure 61 Summary
7. If updating the schedule is necessary, select Save Repository and click Update. Continue to
follow the wizard to update the scheduling tasks.
When the update is complete, click Refresh to update the data view of the selected tab.
To schedule a repository backup to a local path:
1. From the menu bar, click Administrative Tools to open the drop-down menu.
2. Clear the option Save to a network path using the following credential
3. Set the values for the following applicable options and click Next:
Task name
Location of the path
NOTE: The format of the location of the network path is: c\BackupRepository.
Figure 62 Schedule Task
4. Set the values for the Task name, Path on and click Next.
5. Review the summary of task and click Save.
Repository Backup 53