Before you use the encryption setup wizard for the first time, you should also have a detailed
configuration plan in place and available for reference. The encryption setup wizard assumes the
following:
You have a plan in place to organize encryption devices into encryption groups.
If you want redundancy and high availability in your implementation you have a plan to create
high availability (HA) clusters of two encryption switches or blades to provide failover support.
All switches in the planned encryption group are interconnected on an I/O synch LAN.
The management ports on all encryption switches and DCX CPs that have encryption blades
installed have a LAN connection to the SAN management program, and are available for
discovery.
A supported key management appliance is connected on the same LAN as the encryption
switches, DCX CPs, and the SAN Management program.
An external host is available on the LAN to facilitate certificate exchange.
Switch KAC certificates have been signed by a Certificate Authority (CA), and stored in a known
location.
Key management system (key vault) certificates have been obtained and stored in a known
location.