FW 07.00.00/HAFM SW 08.06.00 McDATA SANpilot User Manual (620-000160-230, April 2005)

3
3-32
McDATA® Sphereon 3032 and 3232 Fabric Switches Installation and Service Manual
Diagnostics
13
Verify facility AC power connections.
a. Ensure both AC power cords (PS0 and PS1) are connected to
the rear of the switch and to facility power receptacles. If not,
connect the cords as directed by the customer.
b. Ensure associated facility circuit breakers are on. If not, ask the
customer set the circuit breakers on.
c. Ensure the AC power cords are not damaged. If damaged,
replace the cords.
Was a corrective action performed?
YES NO
Go to step 15.
14
Verify operation of both power supplies.
a. Inspect the power supplies and ensure the green LEDs
illuminate.
b. At the Hardware View, observe the graphics representing the
power supplies and ensure a failure symbol (blinking red and
yellow diamond) does not appear.
Is a failure indicated?
YES NO
The switch appears operational.
15
Ensure both power supplies are correctly installed and seated in the
CTP card. If required, partially remove and reseat the power supplies.
Was a corrective action performed?
YES NO
Go to step 17.
16
Verify operation of both power supplies.
a. Inspect the power supplies and ensure the green LEDs
illuminate.