HP StorageWorks HSG60 and HSG80 Array Controller and Array Controller Software Command Line Interface Reference Guide (EK-G80CL-RA. C01, March 2005)

CLI Command Descriptions
157HP StorageWorks HSG60 and HSG80 Array Controller and Array Controller Software
Command Line Interface Reference Guide
In dual-redundant mode, if both controllers cannot be shut down, both
controllers and associated battery chargers remain on.
Example
To power off the disk units and the enclosure in 10 seconds (BATTERY_OFF and
NO_OVERRIDE_BAD_FLUSH are the defaults), enter:
POWEROFF SECONDS=10
Table 5: POWEROFF Switch Settings
Battery
Switch
Override Switch
Flush
Results
Action
BATTERY_ON OVERRIDE_BAD_FLUSH Success Controller and units in the enclosure
shut down, and the ECB charger
remains on.
BATTERY_ON OVERRIDE_BAD_FLUSH Failure Controller and units in the enclosure
shut down, and the ECB charger
remains on.
BATTERY_ON NO_OVERRIDE_BAD_FLUSH Success Controller and units in the enclosure
shut down, and the ECB charger
remains on.
BATTERY_ON NO_OVERRIDE_BAD_FLUSH Failure Nothing is shut down, the ECB
charger remains on, and the user is
notified of a bad flush.
BATTERY_OFF OVERRIDE_BAD_FLUSH Success Controller and units in the enclosure
shut down, and the ECB charger turns
off.
BATTERY_OFF OVERRIDE_BAD_FLUSH Failure Controller and units in the enclosure
shut down, and the ECB charger turns
off.
BATTERY_OFF NO_OVERRIDE_BAD_FLUSH Success Controller and units in enclosure shut
down, and the ECB charger turns off.
BATTERY_OFF NO_OVERRIDE_BAD_FLUSH Failure Nothing is shut down, the ECB
charger remains on, and the user is
notified of a bad flush.