Installation and Upgrade Guide

G06.24 Software Installation and Upgrade Guide528593-005
2-1
2 G06.24 Upgrade Checklists
Use the checklist in Table 2-1 as you perform the tasks required to upgrade to the
G06.24 RVU and the checklist in Table 2-2 to record the information needed when
performing these tasks.
Task durations are included in Table 2-1. Most of these baseline durations were
established on an NonStop S72002 server running the G06.12 RVU under minimal
load (one user).
Note that these durations generally do not include operations such as starting a TSM
Service application or performing a System Discovery in the TSM or OSM Low-Level
Link Application.
If you use DSM/SCM to manage OSS files, the Build/Apply operation is longer (about
an hour).
G06.24 Upgrade Checklist
Table 2-1. G06.24 Upgrade Checklist (page1of3)
Task Description
Minimum
Duration Documentation
Done
?
1. Install the latest
DSM/SCM SPR, SWID
(if necessary)
40 minutes Appendix B, Installing the Latest
DSM/SCM SPRs and Client
Software
2. Run Install^Templates
macro
5 minutes If Running INSTALL^TEMPLATES
Is Required on page B-13.
3. Install the DSM/SCM
client version
5 minutes Install the DSM/SCM Client From
ZDSMSCM on page B-18
4. Install required or
recommended fallback or
interoperability SPRs (if
necessary).
0.0 minutes
*
Section 3, Installing SPRs Before
Upgrading to the G06.24 RVU
Appendix A, Using DSM/SCM to
Install SPRs
5. Save current system
configuration file
<1 minute Save the Current Configuration
File (CONFxxyy) on page 4-1
6. Upgrade system console
software
90 minutes Upgrade the System Console
Software on page 4-2
7. Verify system operations 15 minutes Verify System Operations
on
page 4-3
8. Receive G06.24 RVU
SUT into the DSM/SCM
software archive
33 minutes
(Full SUT --
all products)
Receive New Software Into the
Archive on page 5-3 and follow
Alerts on page 5-1.
9. Create G06.24 software
configuration revision
1 minute Create a New Software Revision