5.
Align and install the switch module into the chassis.
6. Do one of the following:
o If the uplink module is already installed, verify the switch module powers on and the health LED is
green.
o If the uplink module is not installed, install the uplink module before verifying LEDs.
For more information, see "Installation information and guidelines (on page 16)."
7. Install the access panel.
8. Install the chassis in the rack.
9. After both components have been installed, verify the switch firmware is at the recommended firmware
version. For more information, see the HP website (http://www.hp.com/go/moonshot/download).