Installation Guide

Skim coat is recommended to be 1/8"
- 1/4" thick and the tile/stone is to be
installed while the skim coat is wet.
CAUTIONS: This product shall not be
used in the following applications:
• As a backer board in balcony railings
and balcony parapet walls
• HardieBacker 500 may not be used
to a height exceeding through the
second-story above grade or greater
than 30 feet above grade.
¹ See IRC Table R703.4, IBC §2101.2 and
§1405.10
VINYL AND RESILIENT FLOORING (Interior Application Only)
Materials Required
1 | Fasteners
Minimum 7/8” long galvanized or polymer-coated 18-gauge chisel point staples
with 1/4”crown.
Minimum 7/8” long galvanized ring shanked underlayment ooring nails.
• Fasteners should be long enough to reach the bottom of the suboor, but not
penetrate it.
• Avoid using resin, rosin or cement-coated fasteners that can discolor vinyl ooring.
2 | Patch
Use the cement-based, rapid-setting patching compound recommended by the
oor covering manufacturer.
• Do not use a gypsum-based patch. Follow the patch manufacturer’s instructions.
Preparation for Underlayment
1 | Ensure subfloor is structurally sound and properly installed
On existing floors:
HardieBacker
®
cement board may be installed under or over Vinyl Composition Tile
(VCT) and other resilient ooring. For best results, remove existing oor covering,
especially if it is in poor condition.
• If installing HardieBacker cement board over existing oor, ensure the oor is at
and oor covering is thoroughly adhered to the suboor.
On all floors:
• Ensure suboor is not damaged. Replace any loose, warped, uneven or damaged
sections of oor.
• Make sure suboor is dry, level and fastened correctly. All fasteners must be
countersunk or ush with the suboor. All seams or other areas that are not level
must be sanded at.
• Suboor must be free of all debris, oil, grease, paint or other foreign substances.
2 | Basements and crawl spaces
• Crawl spaces must be well ventilated with a minimum of 18” between the ground
and joists. A vapor barrier over the ground is required.
5 | English