INSTALL THE SECOND DRIVE PIPE CARRIER STRUT AND ASSEMBLY.
1. You will continue to work away from the motor reference point.
2. The strut for the second drive pipe carrier is installed with strut beam clamps at a
location that is 11’ from the first drive pipe carrier location.
3. Loosely install a DPC-A to that strut and adjust for Drive Pipe Center line AFF.
4. Secure all nuts to mount the assembly to the strut.
FIGURE 7 - SECOND DPC
INSTALL THE SECOND DRIVE PIPE SEGMENT TO THE FIRST DRIVE PIPE
SEGMENT.
1 Insert a drive pipe segment through the second DPC-A towards the first drive pipe
segment.
2 Insert the drive pipe segment non-swaged end first through the second DPC-A.
3 Allow the non swaged end of Drive pipe segment 2 to go over the swaged end of
drive pipe segment one.
4 Insert the second drive pipe fully over the swage of drive pipe 1 segment.
5 Splice the Drive Pipe segments together.