Installation Guide

2. Check the Valve Operation
WARNING: Risk of personal injury. Wrap a cloth towel around the pipe plug to
prevent water spray. Water will purge from the supply tube when you remove
the plug.
Thread a 3/8 pipe plug into the top of the spout supply tube.
Ensure that the valves are in the closed position. Turn the cold valve fully
couterclockwise. Turn the hot valve fully clockwise.
Turn on the main water supply.
Check the complete installation for leaks with the valve closed and open.
Repair leaks as needed.
Close both valves and turn off the main water supply.
Carefully loosen the pipe plug to remove pressure.
Thread the pipe plug back into the spout supply tube.
Install the cardboard plaster guards over both valves and the spout supply tube.
Vérifier l’opération de la valve
AVERTISSEMENT: Risque de blessures corporelles. Enrouler une serviette
autour du bouchon du tuyau pour empêcher l’eau de gicler. L’eau purgera du
tube d’alimentation lorsque le bouchon sera retiré.
Visser un bouchon de 3/8 (1 cm) sur le tuyau d’alimentation du bec.
S’assurer que les valves soient en position fermée. Tourner la valve d’eau froide
complètement vers la gauche. Tourner la valve d’eau chaude complètement vers la
droite.
Ouvrir l’alimentation d’eau principale.
Vérifier qu’il n’y ait pas de fuites dans l’installation avec la valve fermée et
ouverte.
Réparer les fuites au besoin.
Fermer les deux valves et l’alimentation principale d’eau.
Dévisser doucement le bouchon du tuyau de manière à libérer la pression.
Brass Washer
Rondelle en laiton
Arandela de latón
3/8" Pipe Plug
Bouchon tuyau de 3/8"
Tapón de tubo de 3/8"
Spout Supply Tube
Tuyau d'alimentation du bec
Tubo de suministro del surtidor
Supply Tube Shoulder
Épaule de tube d'alimentation
Reborde del tubo de suministro
Kohler Co. 9 1089448-2-A