10
2. Front Post Installation
Remove six M8x15 Bolts (41), six Ø8 Spring Washers (64), and six Ø20xØ8 Curve
Washers (42) from the Main Frame (1). Remove bolts with the 5mm Allen Wrench
provided.
Put the cable end of resistance cable of Tension Control Knob (54) into the cable lock of
Tension Cable (30), see Figure A.
Pull the resistance cable of Tension Control Knob (54) up and force it into the slot of metal
bracket of Tension Cable (30), see Figure B.
Insert the metal fitting on the resistance cable of Tension Control Knob (54) into the hole at
the end of the slot in the metal bracket of Tension Cable (30), see Figure C.
Connect the resistance cable of Tension Control Knob (54) to Tension Cable (30) complete,
see Figure D.
Connect the Sensor Wire (68) from the Main Frame (1) to the Extension Sensor Wire (67)
from the Front Post (5).
Insert the Front Post (5) onto the tube of the Main Frame (1) and secure with six M8x15
Bolts (41), six Ø8 Spring Washers (64), and six Ø20xØ8 Curve Washers (42) that were
removed. Tighten bolts with the 5mm Allen Wrench provided.
Tool:
Allen Wrench 5mm
68
67
5
1
30
54
42
41
42
41
64
64
A
B
C
D
54
30
54
30
54
30
54
30