Installation guide

Delivery
OFFLOADING
The purchaser is responsible for offloading the tank and any accessories using the following method:
 must not be in contact with the tank)
Do not lift the tank if it contains any water. Maintain control over the tank when lifting by use of guide ropes. Do not allow the tank
to impact against other objects. If the tank is stored on site prior to installation, it must be upright on a flat and level ground where it
cannot be punctured or otherwise damaged.
PAYMENT
EPS require payment in full for the system on the day of delivery, unless other credit terms have been agreed.
SCOPE OF SUPPLY
EPS will deliver 1 No. complete Bison ASP system to the site complete with temporary cover.
Once the system is installed and has been connected to the sewers and power is available to the unit, EPS should be contacted to com-
mission the system.
We require 10 working days notice for this.
At this stage the air blower and control box will be installed, wired and commissioned by EPS personnel or approved agents.
8