Product specifications

530.PROD.GB.3 : 560.GEN.MOD_XCHNG.SEP.NONE.GB.2 Black 47
©, MEI., 1994.47
CashFlow
530 Changegiver Product Maintenance Handbook
When refitting the separator, position the right hand clip first, then
the left hand clips. Make sure that all three clips are seated correctly
as it is possible to snap the separator into place without the clips
being fitted correctly. If this happens you may get coin jams.
REMOVING THE SEPARATOR SOLENOID BANK
1 Remove the separator from the acceptor.
2 The solenoid bank is held in position with a retaining
spring.
3 Squeeze together both sides of the spring, unhook and
bring forwards.
4 The spring is held in place at the bottom by two small
clips. Lift the spring up and over these clips.
5 Lift the solenoid bank from its resting position. Make a
note of the way the cable from the solenoids is routed.
Once removed, you will need to re-route this cable after
refitting a new solenoid bank.
Solenoid Bank
Spring Clip