Installation Guide

© Metal Sales Manufacturing Corporation / Subject to change without notice / Effective 6/14
21
CLASSIC RIB
®
1. Apply a row of Tape Sealant across the top leg of the Eave Molding along the width of the
building.
2. Align and place Inside Closures over the Tape Sealant. It is critical that Inside Closures are
square to building as this will control the alignment of the panels. (See page 24 to check
building square).
3. Apply a row of Tape Sealant across the top of the Inside Closure (not shown for clarity).
POST FRAME PANEL INSTALLATION
NOTE: -Eave Molding, Gutter and Valley Flashings must rst be installed before panel installation can begin.
-Panels can be installed going from either left to right or right to left / looking from eave to peak.
INSTALLING FIRST PANEL
INSTALLING INSIDE CLOSURES
1. Install the rst panel over the Inside Closure allowing desired overhang. Make sure the panel is
square to the eave and rake.
2. Fasten through panel, closure, and sealants into decking with appropriate amount of fasteners to
meet local building code. (see fastening pattern on page 6). Fasteners must penetrate closure and
sealant.
3. After securing panel at eave, repeat the fastening pattern at all panel support locations.
STEP
1
STEP
2
FASTENER
INSIDE CLOSURE
w/ TAPE SEALANT
TAPE SEALANT
INSIDE CLOSURE
ROOF PANEL