User guide

27
Chapter 2 - Installation Quick Start
Powering Up
Before powering-on the MultiArray verify the following information:
Verify that both power cords are attached to the unit and to a live AC outlet. Both of the
power cords must be plugged in for the system to operate properly.
Verify that the slide switch on all four power modules is set for the appropriate AC voltage
(either 115V or 230V).
Verify that the power switch for each of the four power modules is on before master power
switches are turned on.
To power-on the MultiArray:
Press the Master Power switches on the front of the chassis to the On Position. Then, ensure
that the populated subsegments are also powered up. See Figure 2-18.
11511 5
11511 5
Master Power Switches
BCD Display and
Toggle Switch
Individual Segment Power Switches
Figure 2-18. On/Off Switch
Once the unit has been powered, refer to the Power-Up Notes that follow prior to loading any
software.
Power-Up Notes
Note 1: For the CD-ROM and Floppy drives to be initialized on each SBC, toggle the BCD
display to match the segment. Power-on that segment. Once it has booted, change the BCD
display to the next segment and power it on. Continue this process until all populated segments
are on.
Note 2: If the disk is changed in the CD-ROM or floppy drive, the only SBC that will recognize it
will be the segment selected on the BCD display. The disk (CD or floppy) must be ejected and
reinserted for each segment in order for that segment to see the new disk.
Troubleshooting Power-Up
This system contains two sets of dual power supplies. The right set powers the first five
segments and the left set powers segments 6-9. If a group of segments does not power up,
check that the power switches for each power system are turned on. All individual power supply
module switches should be left on and the master power switches used to turn power to the
segments on and off.