Instruction Manual

10
© 2013 Nor-Lake, Inc 07/13 Rev. F 132617
Place the second panel in position next to the first floor panel but
DO NOT LOCK!
Shim the second panel, where necessary, using the same procedure
as was used on the first panel. When all four edges of the second
floor panel are properly shimmed, lock the two panels securely
together. Using the same technique for leveling, check the levelness
of the two sections in all directions by placing the level across the
joint at several points and, again, check the levelness of the floor
panels in the direction of the panel joint.
Refer to the erection diagram and install the remainder of the floor
panels using the same procedure as was used for the first and
second floor panels. When all of the floor panels are installed and
leveled perfectly, check the section latches for full and complete
locking.
Trim excess vapor barrier.
flooR insTallaTion (shim levelinG meThod)