Video Conference Bridge Hardware & Installation Guide

Chapter 2 - Hardware Installation
2-22
3. Release the clasp locks at the bottom, and lift the MGC-50 top cover.
Figure 2-12: Unpacking the MGC-50
4. Lift the MGC-50 unit and remove the package base.
5. Lower the MGC-50 unit, placing it on the surface.
If you are rack mounting the MGC-50, allow a minimum clearance of 3
inches above the unit.
Foam Blocks
Foam Blocks
Wood Packing Case