User`s guide

INSTALLATION
Eaton 5125 Rack-Mount UPS (5000/6000 VA) User's Guide S 164201541 Rev D
www.eaton.com/powerquality
31
To install the REPO switch:
1. Verify that the UPS is off and disconnected from utility power.
2. Remove the REPO connector from the REPO port on the UPS rear
panel (see Figure 14).
3. Connect isolated, normally‐open, dry contacts (rated to handle
60 Vdc maximum, 30 Vac RMS maximum, and 20 mA maximum)
across the REPO device to Pin 1 and Pin 2 (see Figure 14).
Use stranded, non‐shielded wiring, size 0.75 mm
2
–0.5 mm
2
(18–20 AWG).
NOTE A separate contact must simultaneously cause UPS input AC power to be removed.
Pin 1 Pin 2
Figure 14. REPO Connector
4. Reconnect the REPO connector to the REPO port.
5. Verify that the externally-connected REPO switch is not activated to
enable power to the UPS output.