3 Setting the nozzle pressure
The pressure must be set by a qualified professional.
The boiler must be commissioned after having checked the points
covered in this chapter: Final checks before commissioning.
- Connect the manometer to the left or right pressure outlet on the
manifold.
- Turn the boiler on. Set the boiler thermostats to maximum.
- Unscrew the protection cap on each valve.
- Set the pressure on the left and right valves as shown in the table
in the relevant chapter: Pressure settings and calibrated nozzle
markings. Use the screw located under the protection cap. The
pressure must be the same on both pressure outlets on the
manifold.
- Replace the protection caps.
When replacing a gas valve:
- Carefully set the pressure and progressivity at the opening as
described in this chapter.
Pressure socket