Manual

29
The PCL inverter chargers can operate like battery chargers converting incoming AC power into
DC recharging power. The 2000W has a 65A max while the 3000W has a 75A max adjustable
battery charging.
11
11 Maximum Utility Charging
The default is the maximum value (65A-2KW,
75A-3KW), with a 5A minimum.
The purpose of this setpoint is to protect the batteries from being over discharged. It assumes
that Battery Priority is set on Program 01. If utility power is not available, the designated setpoint
will cut of all working loads. Upon Utility power being detected, the Utility power/Generator will
then power the loads.
12
12 Low Battery Voltage Setpoint
The default is low battery voltage alarm set
point. The range is from 10.5V to 12.5V.if the
voltage set by user is below default point ,the
default is low battery voltage alarm point.
Increment of each click is 0.1V for 12V
Low battery voltage
inverter transfer to Utility
V
BATT
This setpoint indicates the recovery voltage to normal operation when a battery has been
over-charged or is over the voltage limit. The inverter charger will be in a fault state if the battery
voltage is above this designated setpoint and resume normal battery operation when reaching
this set point.
13
13 Over-Voltage Battery Recovery
Over-voltage battery
recovery
Over-voltage battery recovery can be set
between 13.0V to 15.5V. otherwise it is
output of bypass setting range is from
13.0Vto 15.5Vfor 12V,if the voltage set by
user Increment of each click is 0.1V for 12V
V
BATT
When the PCL inverter charger experiences a fault, the unit will automatically stop functioning
but have the option of having a fault alarm as well. Users may toggle this switch if they do not
want the alarm sound.
18
18 Alarm Control / Behavior
Beeps while function keys
are pressed