Figure 1-13 Conext SW DC Connections
Battery or Battery
Enclosure
(2)(a)
(1)
Route the DC cables from the battery bank to the DC Switchgear.
(2) Install a DC fuse (a) on the positive cable near the battery terminal.
(3) Open the DC circuit breaker on the DC Switchgear.
(4) Connect one connector on the POSITIVE (+) cable to the POSITIVE terminal on the DC
Switchgear. The connector goes on first, then the flat washer (steel), then the 3/8”
(9.5mm) bolt (brass).
(5) Connect the other connector to the POSITIVE (+) terminal on the battery.
(6) Connect one connector on the NEGATIVE (–) cable to the BATTERY NEGATIVE
terminal on the DC Switchgear.
(7) Connect the other end of the cable to the NEGATIVE (–) terminal on the battery.