Installation Manual

Pre-Installation and Wall-Mounting
2–4 975-0239-01-01 Rev J
This manual is for use by qualified personnel only
Clearance Requirements
Provide at least 91 cm (36 in.) of clearance in front of the inverter, and a minimum
of 15 cm (6 in.) of clearance at the top and bottom of the inverter for ventilation.
Ensure the vents remain unobstructed, and that the Conext XW+ Power
Distribution Panel door has adequate room to fully open.
Knockout Selection
The Conext XW+ Inverter/Charger, Conext XW+ Power Distribution Panel, and
Conext XW+ Conduit Box are equipped with nested dual knockouts for wiring
through conduits.
Read Chapter 3, “Wiring the Conext XW+ and Conext XW+ PDP” and choose the
knockouts for your installation.
Figure 2-1 Example of clearance requirements for a Conext XW+ with PDP
Note: Do not drill, cut, or punch holes into the Conext XW+ Inverter/Charger,
Conext XW+ Conduit Box or Conext XW+ Power Distribution Panel. Use only the
knockouts provided for conduit entry.
AC1
AC2
Event
Equalize
kW
A
Charging
!
Inverting
Min. clearance
Min. clearance
at top:
152 mm (6 in.)
914 mm (36 in.)
in front:
XW-NA-Install.book Page 4 Wednesday, August 12, 2015 2:23 PM