Wiring the Conext XW+ Inverter/Charger with a PDP
975-0239-01-01 Rev J 3–17
This manual is for use by qualified personnel only
Making AC Connections
This section provides instructions for making AC connections between the
Conext XW+ Inverter/Charger and the Conext XW+ Power Distribution Panel
(using the pre-installed AC cables in the PDP) and between the PDP and your
inverter load sub-panel.
Note: Install an inverter load sub-panel and AC conduit before completing your
Conext XW+ installation. For more information, see “AC Wiring to the Inverter
Load Sub-Panel” on page 3–26.
Note: Do not use a GFCI equipped AC source to power either the Grid (AC1) or
Generator (AC2) inputs. The AC input filters on the Conext XW+ may cause
nuisance tripping of ground fault protected outputs.
NOTICE
BACK FED AC POWER
Back fed AC Power can damage equipment. Do not wire the inverter’s AC
output port directly to the utility line or generator output.
Failure to follow these instructions can result in damage to equipment.
Note: Wiring the inverter’s AC output to the utility or generator output will cause
severe damage to the inverter which is not covered under warranty.