Installation Manual

Wiring the Conext XW+ and Conext XW+ PDP
3–28 975-0239-01-01 Rev J
This manual is for use by qualified personnel only
4. Connect L1 and L2 from the input side of the 60 A, 120/240 VAC, two-pole,
Type QOU AC1 breaker (L1 and L2 jumpers) to the main AC panel (utility
grid).
Basic Functional Test – Single Inverter
Complete the following steps to perform a basic functional test of the Conext
XW+ Inverter/Charger. If any test fails, refer to the Troubleshooting section in the
Conext XW+ Inverter/Charger Owner’s Guide for assistance.
Figure 3-15 Wiring the PDP to the Inverter Load Sub-Panel or Utility Grid
AC INAC OU T AC IN
GRID
(AC1)
AC
LOAD
GEN
(AC2)
NL1L2NL1L2NL1 L2
L2
L1
1
2
1. Main utility panel
2. Inverter load sub-panel
Actual wiring requirements may vary.
Cable routing may vary. See Knockout Selection
on page 2-5 and Communications Network
Preparation on page 2-12.
For torque values, see page 2-16 and 2-17.
LEGEND
Grounding
wire
Neutral
Hot L1
Hot L2