Installation Manual

Wiring the Conext XW+ and Conext XW+ PDP
3–36 975-0239-01-01 Rev J
This manual is for use by qualified personnel only
Wiring Additional Conext XW+ units with a PDP
This section provides instructions for making AC and DC connections between
multiple Conext XW+ units and a Conext XW+ Power Distribution Panel, using the
cables that are included with each PDP and Conext XW+ Connection Kit for INV2
INV3 PDP.
To install a balanced three-phase system, see “Wiring a Balanced Three-Phase
System” on page 3–54.
Pre-Installation Steps
Note: The installation steps described in this section require a Conext XW+
Connection Kit for INV2 INV3 PDP (part number 865-1020-02) and Conext 120/
240VAC Breaker Kit (part number 865-1215-01) for each additional Conext XW+
Inverter/Charger.
For more information, contact your local Schneider Electric Sales Representative
or visit our website at: http://www.schneider-electric.com/sites/corporate/en/
support/operations/local-operations/local-operations.page
NOTICE
EQUIPMENT DAMAGE
Be sure to finish all wiring (AC, DC, Xanbus, communications) when installing
additional Conext XW+ units including “Installing AC sync and Xanbus cables”
on page 4–5 prior to powering up the system.
Failure to follow these instructions can result in equipment damage.
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Apply appropriate personal protective equipment (PPE) and follow safe
electrical work practices. See NFPA 70E or CSA Z462.
This equipment must only be installed and serviced by qualified electrical
personnel.
Never operate energized with covers removed
Energized from multiple sources. Before removing covers identify all
sources, de-energize, lock-out, and tag-out and wait 2 minutes for circuits
to discharge
Always use a properly rated voltage sensing device to confirm all circuits
are de-energized.
Failure to follow these instructions will result in death or serious injury.